Castalia’s John Sachs shares his thoughts on recent developments in the sector.


Like many in the industry, we have spent the last few weeks trying to understand how the COVID-19 crisis will impact electric utilities and IPPs in emerging markets. Our early fears, raised in our late April blog “Assessing the impact of force majeure on emerging markets PPPs”, are starting to come true. The COVID-19 pandemic is putting many state-owned electric utilities in emerging markets under increasing financial stress and jeopardizing not only their IPP programs but also risking wider contagion in the economies.  We are seeing this across the globe, IPPs receiving notices of payments being deferred, or threats of declaring force majeure, often with no details of for how long or if or when the IPPs will ever be made whole. The latest example of this financial stress, and the threat of declaring force majeure, was reported this week in Kenya.

This financial stress—resulting from a mix of reductions in demand, consumer tariff forgiveness and deferrals granted by the Governments for social reasons, and greater difficulty in accessing finance—is likely to last beyond the immediate period of emergency pandemic response. An additional source of stress may also be originating from the independent power producers (IPPs), who in some cases may be unable to fully satisfy their Operations and Maintenance responsibilities, import parts, or be faced with foreign exchange constraints due to the pandemic.

What we recommended in April remains even more true today, “Governments and authorities managing infrastructure concessions should get ahead of this through a rapid assessment of their PPP portfolios to identify and measure risk factors, including exposure under their force majeure clauses, develop action-oriented steps to manage the risks and, when appropriate, commence early engagement with private sector operators.” This early engagement to amicably work-out a solution with investors and their lenders could help avoid damage to their investment climates, cost of capital, and resulting cost of service from future PPP projects.

Infrastructure projects, and public-private partnerships in particular, around the globe and in all sectors have felt the impact of the COVID-19 pandemic, as supply chains and customer demand have been disrupted and health recommendations have changed the way business is conducted.

Many countries have taken action to limit the virus spread through social distancing policies, limiting work to only essential activities, closing schools and restricting travel. Approximately 90 percent of the world’s population has faced travel restrictions amid the COVID-19 pandemic.

User-fee concessions (including roads, carparks, airports, ports, ferries, etc.) are under great stress due to reduced demand. According to the International Bridge, Tunnel & Turnpike Association (IBTTA), traffic on tolled facilities in the United States is down by 50 to 90 percent. Availability fee-based projects may come under increased pressure as public sector counterparties face declining revenues and competing demands during the pandemic. While for many projects the problem is one of near-term liquidity, the long-term outlook for these assets could be in doubt if GDP growth forecasts are revised downward. The pandemic has brought into focus the risk to the financial performance of the PPP infrastructure projects and their ability to stay under construction, to operate and provide maintenance according to expectations, and to service debt.

Governments and authorities managing infrastructure concessions should get ahead of this through a rapid assessment of their PPP portfolios to identify and measure risk factors, including exposure under their force majeure (FM) clauses, develop action-oriented steps to manage the risks and, when appropriate, commence early engagement with private sector operators.

Force Majeure in PPP Agreements

Most international PPP agreements explicitly include FM clauses. FM clauses define the circumstances beyond a contracting party’s control in which a party’s nonperformance may be excused. At a minimum, such clauses typically allow an extension of time for performance and relief from liability for nonperformance by the party timely invoking it; in some cases they permit additional relief, such as an ability to terminate the contract and even in a minority of cases a pass-through of costs. As a creature of contract (rather than relief provided under statutory or common law), FM clauses can vary widely and the scope of events that qualify as FM and the relief available to a party impacted thereby will depend upon the specific language used in a contract. There is a lot of variability in PPP agreements, and the words chosen are important.

Certain claims of relief can be expected to be made under the most typical formulations of FM clauses in PPP agreements. For projects that have not yet achieved commercial operations, this may include deadline extensions, waiver of delay liquidated damages (LDs) and potentially pass-through of additional costs. For projects that are operational, this may include adjustments to performance standards, waiver of performance LDs, pass-through of additional costs and excuse from performance.

Impact on PPPs is Not Universal

While some projects deemed essential are progressing despite the pandemic, others are halted. In addition, some projects may be delayed due to supply chain disruptions of equipment and materials—such as structural steel from Asia. It is too early for hard figures, as the impact is not universal and is rapidly evolving—some projects continue and are able to overcome the crisis, some areas are harder hit than others. Disparate impacts are seen in both emerging markets PPPs and PPPs in established markets. There is only anecdotal information currently, such as:

  • In mid-March, the mayor of Boston, Massachusetts halted all municipal construction projects for a minimum period of two weeks, which period has subsequently been extended.
  • In Australia, construction projects continue and are exempt from the lockdown, with companies implementing staggered shifts and social distancing.
  • In Bangladesh, the government suspended the construction works of all major infrastructure projects, reported to be worth more than US$30bn, including bridges, tunnels, power plants and rail.
  • Despite early signals that supply chain impacts could lead to significant decline in US renewables, the US the Department of Energy is projecting annual wind and solar capacity additions at only 5 percent and 10 percent lower, respectively, due to the pandemic.
  • Reports suggest that the construction plans for Nord Stream 2 remain unaffected by COVID-19 and the developer expects no impact from the social distancing measures on the implementation of the project.

There is a heightened concern about public sector entities’ ability to financially perform in a timely manner in some countries. The risk of increased delays in payments is due largely to further pressure on the governments’ finances, derived from a depressed economy. Governments and PPP agencies not only face concerns about the financial performance of the PPP projects, but also the operational performance in light of COVID-19.

Assessment by PPP Agencies and Governments in Emerging Markets

The availability of specific types of FM relief will depend upon the contractual language included in the PPP agreement. However, under some of the most common FM contractual language, the key questions PPP agencies should consider include the following: Is the private partner prevented from performance? Was the impact of COVID-19 something the private partner could have provided against? Are impacts covered under an insurance policy, or should they have been? Has the private partner taken reasonable steps to avoid or overcome the impacts of COVID-19? Are the remedies sought by the private partner contemplated by the PPP agreement? Does the private partner’s request for FM relief comply with the process requirements in the PPP agreement?

Action for Emerging Markets Governments to Take Now

  • Stay up-to-date regarding the spread and impact of COVID-19 locally
    • Stay abreast of the latest information related to the spread of COVID-19 locally, including the number of confirmed cases, number of deaths and capacity of hospitals, as the spread may impact claims for FM relief.
    • Refresh the base of knowledge about their concession agreements, financial exposure under FM and financial models for each project to be ready to estimate possible FM exposure, and/or defend against unjustified FM claims.
    • Learn how other PPPs and actors are addressing the impacts of COVID-19. Some actors may have crafted solutions to overcome the effects that could be applied to other PPPs.
  • Assess the entire portfolio of PPP projects
    • PPP agencies should assess the financial and operational performance of all PPP projects in their portfolio, identify the risks posed by COVID-19 to such projects and review the FM provisions contained within the applicable PPP agreements to determine the likelihood that a private partner may currently be entitled to or may soon be entitled to make a claim for FM relief.
    • If it is determined that the private partner of a particular project is likely to claim FM relief, PPP agencies should consider what steps will be required of them in response. Will the PPP agency be obligated to respond or take action within a set period of time under the PPP agreement? Will a claim for FM relief under this project trigger obligations under other contracts? Are there public notice requirements for the PPP agency under law?
  • Take proactive steps to prepare for claims
    • Rather than wait for a partner to make a claim of FM and potentially end up in a dispute, engage with partners to determine the partner’s assessment of the risk of COVID-19 to its projects and its plans for addressing such risk.
    • Consider on a project-by-project basis whether to negotiate and implement a COVID-19 response plan for the project in which the PPP agency and private partner agree to actions that each party should be taking now to address COVID-19, actions that each party will take in the future and the triggers for such actions.
    • If necessary, consider on a project-by-project basis whether to negotiate amendments to the PPP agreement (for instance, to modify performance targets) in exchange for a waiver of FM relief related to COVID-19.

Other Related Issues

Emerging markets governments should also evaluate how their actions in response to COVID-19 may impact a private partner’s ability to perform under a PPP agreement. Restrictions on gatherings, nonessential businesses and travel may constitute a “Change in Law” under the PPP agreement, entitling the private partner to relief separate from and additional to the FM protections.

Further Information

For further information and discussions on force majeure in the context of COVID-19, please refer to the following: Force Majeure: Jurisdictional Comparison and Practical Legal and Commercial Considerations, Excusing Performance of Commercial Contracts due to ‘Force Majeure’, and Contract Cancellation and the Doctrines of Impossibility and Frustration of Purpose.

Authors

John Sachs

William L. Newton (co-author)

John J. Beardsworth, Jr. (co-author)

Benjamin Y. Cooper IV (co-author)

* Hunton Andrews Kurth LLP, an international law firm with over 1,000 lawyers practicing from 20 offices worldwide, has represented clients throughout Africa, Asia, Europe, Latin America and the United States on PPP transactions and other project matters for more than 30 years.

COVID-19 threatens our health, wealth and welfare. It also threatens to overwhelm our limited resources. We need to think to chart the best course through. No one knows the answers, but rational, evidence-based debate is our best hope.

What’s the cost-effectiveness of various options to fight the pandemic?

What are the economic costs and consequences?

How can essential service providers, like electricity and water utilities, remain solvent while serving customers struggling to pay their bills?

If supermarkets put up prices, is that normal market forces, or price gouging that government should punish?

How can developing countries manage through the pandemic, when social distancing is near impossible, health systems are stretched at the best of times, and fiscal space is non-existent; what can donors and development agencies do to help?

Investors are asking, what will the world look like after the pandemic? Will the location of economic activity shift?

Are different transportation patterns likely?

What does this mean for the value of infrastructure assets and the viability of projects planned before the pandemic?

Now more than ever, we need thinking for a better world. My colleagues and I will be blogging on all these topics, in a rapid-fire format, putting out our ideas, arguing with each, exploring options. Please join our conversation as we help each other find the best way through this crisis.

David Ehrhardt, Chief Executive

WASHINGTON, DC
+1 (202) 466-6790
1747 Pennsylvania Avenue NW, Suite 1200
United States of America

SYDNEY
+61 (2) 9231 6862
Suite 19.01, Level 19, 227 Elizabeth Street
Australia

AUCKLAND
+64 (4) 913 2800
Sinclair House, 3 Glenside Crescent
New Zealand

WELLINGTON
+64 (4) 913 2800
Level 2, 88 The Terrace
New Zealand

PARIS
+33 (0)1 85 64 10 22
3B Rue Taylor
France

BOGOTÁ
+57 (1) 508 5794
Calle 81 #11-08, Piso 5, Oficina 5-121
Colombia

Thinking for a better world.

Castalia-logo-negative-2col
PROJECTS        NEWS        BLOG        CONTACT
© Copyright 2019 Castalia. All rights reserved.  Terms | Privacy | Credits | Sitemap

WASHINGTON, DC
+1 (202) 466-6790
1747 Pennsylvania Avenue NW, Suite 1200
United States of America

SYDNEY
+61 (2) 9231 6862
Suite 19.01, Level 19, 227 Elizabeth Street
Australia

AUCKLAND
+64 (4) 913 2800
74D France Street, Newton South
New Zealand

WELLINGTON
+64 (4) 913 2800
Level 2, 88 The Terrace
New Zealand

PARIS
+33 (1) 73 44 26 97
6 Rue Duret
France

BOGOTÁ
+57 (1) 508 5794
Calle 81 #11-08, Piso 5, Oficina 5-127
Colombia

Thinking for a better world.

Castalia-logo-negative-2col
PROJECTS        NEWS        BLOG        CONTACT
© Copyright 2019 Castalia. All rights reserved.
Terms | Privacy | Credits | Sitemap